| Project Milestone | Days from Appointed Date |
| Milestone-01 | 20% within 180 Days |
| Milestone-02 | 35% within 360 Days |
| Milestone-03 | 75% within 550 Days |
| Milestone-04 | 100% within 730 Days |
| S.No. | Items | Scope (in Km) | Completed (in Km) | Balance (in Km) | Remarks |
| 1 | C&G | 55.18 | 15.37 | 39.81 | 50.102/159.952 Hact. |
| 2 | Embankment Top | 55.18 | 1.940 | 53.240 | |
| 3 | Subgrade Top | 55.18 | 1.750 | 53.430 | |
| 4 | GSB | 55.18 | 55.18 | ||
| 5 | DBM | 55.18 | 55.18 | ||
| 6 | SMA | 55.18 | 55.18 |
| S.No. | Items | Total No. of Structures | Status | Balance |
| 1 | Major Bridge | 1 | ||
| 2 | Minor Bridge | 14 | 02 nos. WIP | |
| 3 | Minor Bridge cum Wildlife Crossing | 1 | ||
| 4 | Minor Bridge cum Underpass | 1 | ||
| 5 | Culverts | 74 | 10 Nos. location WIP | |
| 6 | Viaduct | 2 | ||
| 7 | VUPs | 1 | ||
| 8 | VOPs | 1 | ||
| 9 | LVUPs | 18 | 6 nos WIP | |
| 10 | SVUPs | 4 | 2 NOS. WIP | |
| 11 | Str. Over Gas Pipe Line | 1 | ||
| 12 | AUPs | NA | ||
| 13 | Monket Canopies | NA | ||
| 14 | Interchanges | NA | ||
| 15 | Way Side Amenities | NA | ||
| 16 | ROB | NA |